| Choose Project Information from the Project menu. The Project Information dialog box opens. |
 |
 |
|


 |
| Using the Schedule from drop list, choose Project Finish Date if you want to change when the project ends, or Project Start Date if you want to change when the project begins. |
 |
 |
|


 |
| Click the Start date box and either type a date (using mm/dd/yy format) or click the drop arrow and use the calendar to select a date. |
 |
 |
|

 |
| Click the Finish date box and type a date manually (using the mm/dd/yy format) or click the drop arrow to select a date from the calendar. |
 |